The very top of the roof needed boarding with OSB but it was quite fiddly. The boards were very grippy so I didn’t need scaffolding or ropes.
















This last picture was taken the day before I received a letter from the council advising me that the structure was too tall and would need to be dismantled. I stopped work on the building at this point until the dispute was resolved, so I lost about 4 months from this point.